This form is available only if the Projects feature is enabled on the Enable/Disable Features (CS100000) form.
The form toolbar includes standard buttons and form-specific buttons and commands. For the list of standard buttons, see Form Toolbar and More Menu. The form-specific commands can be shown as buttons on the form toolbar, as commands on the More menu, or in both places. These commands are listed in the following table in alphabetical order.
In this area, you can specify or view the basic settings of a project.
Margin (%) = 100% * (Actual Income - Actual Expenses) / Actual Income
In this dialog box, you specify the details of the service order to be created for the project on the Service Orders (FS300100) form. The dialog box opens when you click either Create Service Order or Create Appointment on the More menu.
You use this dialog box, which opens when you click the Change ID command, to enter a new ID for the selected project. The dialog box includes the elements described in the following table.
You use this dialog box, which opens when you click Create Template, to create a new project template that is based on the currently selected project. The dialog box includes the elements described in the following table.
In this dialog box, you can specify the new approver to whom you want to reassign the selected record or records. The dialog box opens when you click Reassign.
This tab includes general settings for the project, including its start and end dates, currency, billing requirements, and visibility settings.
This section appears on the form if the Retainage Support feature is enabled on the Enable/Disable Features (CS100000) form. For more information, see Processing AP Bills with Retainage, Processing AR Invoices with Retainage, and Billing a Project with a Retainage Cap.
Completed (%) = (Draft Invoice Amount total + Actual Amount total) / Contract Total
Draft Invoice Amount
Actual Amount total
Cap Amount = Contract Total * Cap (%) * Retainage (%)
This table appears in this section if the Retainage with Steps option button is selected.
This section, which appears on the form if the Construction feature is enabled on the Enable/Disable Features (CS100000) form, contains the settings for the AIA reports to be prepared for the current project.
By using the check boxes in this section, you can specify the functional areas of Acumatica ERP that will be integrated with projects. When this integration is turned on, users can specify projects and tasks in the relevant documents and transactions, and the amounts are recorded in the projects.
This section appears on the form if the Project Quotes feature is enabled on the Enable/Disable Features (CS100000) form.
On this tab, you can add new project tasks and create project tasks based on common tasks if the project is assigned the In Planning, Pending Approval, Active, or Suspended status. You can delete a project task with the In Planning or Canceled status if no documents have been associated with this project task.
The table toolbar includes standard buttons and buttons that are specific to this table. For the list of standard buttons, see Table Toolbar. The table-specific buttons are listed below.
This dialog box, which opens when you click Add Common Tasks on the table toolbar, contains a list of the common tasks that have been defined on the Common Tasks (PM208030) form. You can select the tasks to be added to the project. The table toolbar in the dialog box includes only standard buttons. For the list of standard buttons, see Tables.
This tab lists all the project revenues that can be created manually or generated by the project transactions—that is, that can be generated for the corresponding project, project task, inventory item or cost code, and income account mapped to the account group. The Revenue Budget Update setting on the Projects Preferences (PM101000) form determines the scope of these lines as follows:
For more information, see Project Budget: General Information.
You can use these elements to filter the data of the table. You can also view the pending invoice total amount.
Unit Rate = Amount / Quantity
Amount = Ext. Price – Discount Amount
Completed (%) = (Draft Invoice Amount + Actual Amount + Inclusive Tax Amount + Pending Invoice Amount) / Revised Budgeted Amount * 100%
Completed % = (Draft Invoice Quantity + Actual Quantity + Pending Invoice Quantity) / Revised Budgeted Quantity * 100%
Pending Invoice Amount = Revised Budgeted Amount * Completed (%) / 100 - (Actual Amount + Inclusive Tax Amount + Draft Invoice Amount)
Performance (%) = (Actual Amount + Inclusive Tax Amount) / Revised Budgeted Amount * 100%
Performance (%) = Actual Quantity / Revised Budgeted Quantity * 100%
Retainage Cap Amount = Budgeted Amount * Cap (%) * Retainage (%)
Budgeted Amount
This tab lists all the project costs that can be created manually or generated by the project transactions and commitments—that is, that can be generated for the corresponding project, project task, inventory item or cost code, and expense account mapped to the account group. The Cost Budget Update setting on the Projects Preferences (PM101000) form determines the scope of these lines as follows:
You can use these elements to filter the data shown in the table. You can also view the pending invoice total amount.
Actual + Open Committed Amount = Actual Amount + Committed Open Amount + Inclusive Tax Amount
Variance Amount = Revised Budgeted Amount - (Actual Amount + Committed Open Amount + Inclusive Tax Amount)
PMBudget
PMBudgetProduction
Unit Price = Amount / Quantity
You use this tab to view the budget broken down by account groups.
You use this tab to view the purchase orders and subcontracts that are related to the project.
The tab lists the related subcontracts if the Construction feature is enabled on the Enable/Disable Features (CS100000) form.
This tab appears on the form if the Internal Cost Commitment Tracking check box is selected on the Projects Preferences (PM101000) form.
This tab lists all the project invoices generated during various stages of the project’s execution and the project invoices that have been entered manually. If the billing workflow of the project includes the creation of pro forma invoices—that is, the Create Pro Forma Invoice on Billing check box is selected for the project—the accounts receivable invoices are listed in the same row with the pro forma invoice they were created based on.
If a pro forma invoice has been corrected, the latest generated accounts receivable invoice is listed in the same row with the pro forma invoice. All the previous revisions of the accounts receivable invoices and reversing accounts receivable documents generated for the pro forma invoice are shown at the end of the invoices list.
You use this tab to view change orders related to the project and create new change orders.
This tab appears on the form if the Change Orders feature is enabled on the Enable/Disable Features (CS100000) form.
This dialog box shows the list of reversing change orders corresponding to a change order. The dialog box opens when you click the link in the Reversing CO Nbr. column of the table on the Change Orders tab.
The table toolbar in the dialog box includes only standard buttons. For the list of standard buttons, see Tables.
This tab displays the list of union locals that are associated with the project.
This tab appears on the form if the Construction feature is enabled on the Enable/Disable Features (CS100000) form.
The table toolbar includes only standard buttons. For the list of standard buttons, see Table Toolbar.
You use this tab to view the change requests related to the project and create new change requests.
This tab appears on the form if the Change Requests feature is enabled on the Enable/Disable Features (CS100000) form.
This tab has a table with the list of activities associated with the project. You can associate particular tasks, events, and other activities with the project. Acumatica ERP provides you with a list of predefined activity types; you can add new activity types by using the Activity Types (CR102000) form. To create an activity, email, or task, click the appropriate command and fill in the dialog box.
If the Restrict Employees check box is selected for the project on the Summary tab of this form, only the employees listed on the Employees tab of this form can add activities to the project. Activities cannot be added to the project if it has the Completed or Canceled status. If activities have been added to the project and it has the In Planning status, any related transactions cannot be released until the project status is set to Active.
In addition to the columns described below, the tab includes columns (labeled with icons) that you can use to attach notes and files to the activity and to check what priority level is specified for the activity, whether the activity is completed, and whether any reminders are associated with the activity.
The tab also has the Activity Description area below the table. The area displays the full description provided for the activity selected in the table. To edit the description, click the link in the Summary column of the activity. This opens the Activity (CR306010) form in a pop-up window; on this form, you can add a description and edit other settings corresponding to the activity.
The tab contains a table showing the employees assigned to the project and the relevant settings of each employee. The tab also has the Overrides table, where you can specify the earning type and labor item to be used for the employee selected in the upper table in time activities that are related to the project.
If the Restrict Employees check box is selected for the project on the Summary tab of this form, only the listed employees can create activities and documents associated with the current project, which includes creating activities on the Activities tab of this form, time cards on the Employee Time Card (EP305000) form, and project transactions on the Project Transactions (PM304000) form.
This table displays a list of the employees assigned to the project. For an existing project, you can add or remove employees. The table toolbar includes only standard buttons. For the list of standard buttons, see Table Toolbar.
The table contains the list of earning types and labor items to be used for the employee selected in the upper table in time activities that are related to the current project.
On this tab, you can view, add, modify, and delete the equipment assigned to the project. You can also add new equipment to the project. When you create a new project and select a project template, the system copies the equipment (and the rate items and rates) from the template settings on the Project Templates (PM208000) form.
This tab displays the project address, the billing address of the customer, the contact information for billing, and the tax zone settings of the project.
If the project is created based on a project quote, these settings are copied from the project quote settings on the Project Quotes (PM304500) form. For more information, see Project Quotes: Creation of a Project from a Project Quote.
This section contains the address of the project site where the project work is performed.
If the project is created based on a project quote, these settings are copied from the project quote settings. For more information, see Project Quotes: Creation of a Project from a Project Quote.
If project-specific taxes are calculated in your system, in this section, you can specify the tax zone to be used in the project’s cost documents and revenue documents
This section contains the contact information of the customer for billing purposes. If you are creating a project from scratch, these settings are initially populated with the information specified on the Billing Settings tab of the Customers (AR303000) form, but you can override any of the default settings.
This section contains the billing address of the customer for billing purposes. If you are creating a project from scratch, these settings are initially populated with the information specified on the Billing Settings tab of the Customers (AR303000) form, but you can override any of the default settings.
On this tab, you can specify additional project settings, such as project markups or general ledger accounts and subaccounts that the system uses if the project is selected as the source of a particular account and subaccount.
The elements in this section define the source of the expense accounts to be used in project transactions for purchase orders of the Project Drop-Ship type, as well as the rules for generating documents and transactions in these purchase orders. When you create a new project with a project template, the system copies the settings of the Purchases section on the Project Templates (PM208000) form to this section. If you do not select a project template, the system copies the settings of the Purchases section on the Projects Preferences (PM101000) form to this section.
The settings in this section apply only to purchase orders of the Project Drop-Ship type.
This section appears on the form only if the Inventory and Order Management feature is enabled on the Enable/Disable Features (CS100000) form.
This tab is used to map general ledger accounts to particular project tasks of the current project. The system specifies the project task based on the mapped account in the following places:
For more information, see Default Project Tasks in Record Lines.
If the same mapping should be used for multiple similar projects, you can specify the corresponding rules in a project template on the Project Templates (PM208000) form. The system will copy the mapping rules to the projects created based on this project template.
The accounts and subaccounts specified in this section will be copied to the paychecks and payroll batches related to the project. By default, these accounts are used in paychecks and payroll batches if either of the following conditions is met in the Account Settings section on the General tab of the Payroll Preferences (PR101000) form:
This section appears only if the Payroll feature is enabled on the Enable/Disable Features (CS100000) form.
In the table, you can view, add, change, or delete document-level markups that the system applies to change requests created for the project on the Change Requests (PM308500) form. When you create a new project with a project template, the system copies the default markups from the Defaults tab of the Project Templates (PM208000) form to this section. If you do not select a project template, the system copies the default markups from the Markup section of the General tab of the Projects Preferences (PM101000) form to this section. The default markups can be overridden.
This table appears on the tab only if the Change Requests feature is enabled on the Enable/Disable Features (CS100000) form.
Markup Amount = '''Line Total''' * % Value / 100
Markup Amount = (all the previously applied percentage markups) * Cumulative (%) Value / 100
On the Attributes tab, you can view, add, change, or delete attribute values for the project. The project-related attributes are selected on the Project Attributes (PM202000) form.
This tab displays the approval history of the project. The project is automatically assigned for approval when you click Activate on the form toolbar. Authorized users can approve or reject the selected project on the current form by using the Approve or Reject command, respectively. Alternatively, they can mass-process records that are pending approval by using the Approvals (EP503010) form.
If the record is rejected, a reason is specified during the rejection process, and then the record is returned for editing, that rejection will be listed on the tab, and all other rejections and approvals will be removed.
This tab is available only if the Approval Workflow feature is enabled on the Enable/Disable Features (CS100000) form and an approval map is specified in the Project Approval Map box on the Approval tab of the Projects Preferences (PM101000) form. If no map is specified in this box, projects do not require approval.
The Mailing & Printing tab contains the list of mailings that can be used for emailing the customer pro forma invoices and other documents related to the project, as well as the report and report format to be used for viewing and printing these documents. The tab also contains a table that lists the recipients of a mailing: You click a mailing in the Mailings table, and you can view and edit the default recipients of the selected mailing in the Recipients table.
When a new project is created, the system copies to the project all the rows of the Mailings and Recipients tables of the Mailing & Printing tab of one of the following forms:
You can delete any of these rows, override some of their default settings, and add new rows.
You can add a mailing if it is listed on the Projects Preferences (PM101000) form. When you select a mailing in the Mailing ID column, the values in the other columns are copied from the corresponding columns of the Projects Preferences (PM101000) form, but you can override some values.
You use this table to view and modify the list of mailings that can be used to send project-related emails to the customer. For each mailing, you can select either a report or an email template to be used by default as the body of the email.The table toolbar includes only standard buttons. For the list of standard buttons, see Table Toolbar.
You use this table to view and modify the list of default recipients for the mailing selected in the Mailings table.The table toolbar includes only standard buttons. For the list of standard buttons, see Table Toolbar.
On this tab, you can add, update, and review compliance documents that are related to the project.
This tab appears on the form only if the Construction feature is enabled on the Enable/Disable Features (CS100000) form.
The tab shows the production orders created for the project.
This tab is displayed only if the Manufacturing feature is enabled on the Enable/Disable Features (CS100000) form.
In this dialog box, you can create a production order for the selected task if the project has the Active status and a project task has the Active or In Planning status.
This tab displays estimates linked to the project.
This tab is displayed only if the Estimating feature is enabled on the Enable/Disable Features (CS100000) form.
On this tab, you can specify the settings for generating lien waivers for the payments to AP bills that are related to the current project.
This tab appears on the form only if the Construction feature is enabled on the Enable/Disable Features (CS100000) form, and the Automatically Generate Lien Waivers check box is selected in either or both of the following sections of the Compliance Preferences (CL301000) form: Conditional Lien Waivers or Unconditional Lien Waivers.
The Summary area is used to specify the lien waiver settings for the project.
This table contains the vendor classes of vendors for whose documents the system will automatically generate lien waivers when items and services are purchased from these vendors during the completion of this project. If this project is based on a project template, the table initially contains the vendor classes specified for the project template on the Lien Waiver Settings tab of the Project Templates (PM208000) form. You can change this list of vendor classes.
This tab displays the list of companies and persons involved with the project. The system adds to the table the contacts from the requests for information that have been processed for the project. You can also add contacts manually.
This tab appears on the form only if the Construction Project Management feature is enabled on the Enable/Disable Features (CS100000) form.
By using the side panel, you can view the project that you have opened on the form while simultaneously viewing information related to the project.
The side panel has multiple tabs, each of which you can view by clicking the tab’s icon. These tabs are described below.